Road Construction PROCEDURE (step-by-step):
- Spot marked for cement placement to the designed ratio
- Spreading the required amount of cement (adequate quality)
- Roughly mixing cement and existing soil by graders
- Homogenously mixing soil and cement by soil stabilizer
- Spraying the mixture of Nanoalps and water on the construction
- Mixing soil-cement and mixture of Nanoalps & water by grader
- Compaction of each layer to the required density
- Compaction with pneumatic-tyre rollers
- Smoothing with tandem rollers
- Instantly ready to use for traffic, transportation & infrastructure